The short answer: two sides of the disconnect
Florida's sign specialty electrical license covers fabricating, installing, repairing and wiring electric signs, but not electrical work beyond your sign's last disconnect. Work on your building's side of that point goes to an electrical contractor, and your building official decides how the split plays out on your job.
| Side | What it includes | Who usually works on it |
|---|---|---|
| Your building's side | The breaker in your panel, the branch circuit and a sign outlet at your entrance. | An electrical contractor. |
| The disconnect | The switch that cuts power to your sign, where the circuit enters it. | The point where the two sides meet. |
| Your sign's side | The power supplies in your raceway or sign body, the low-voltage wiring between letters, and the LED modules. | A sign specialty electrical contractor. |
Your building needs a sign circuit before your letters arrive.
The electrical code calls for a sign outlet at each tenant entrance of a commercial building, on a branch circuit of at least 20 amps that serves nothing else. Sign circuits are treated as continuous loads and are limited to 20 amps, except neon circuits at 30 amps.
Your lease decides who pays for that circuit. In one published shopping center's criteria, the landlord provides the main electrical service terminations, while the power and connections for lit signs are the tenant's job. In general, the branch circuit and outlet from your panel fall on the property owner or tenant.
Before your lit sign goes up, check these
- Is there a sign outlet at my entrance?
- Is it on its own 20-amp circuit?
- Is there space in my electrical panel?
- Who does my lease say provides it?
- Does my landlord require a photocell or an outside switch?
See landlord sign criteria for what leases usually say about power.
Every sign circuit needs a disconnect.
Every sign circuit needs a disconnect where the circuit enters your sign, within sight of it, or out of sight but lockable in the off position. A lockable disconnect out of sight carries a warning label.
Pinellas County's inspection instructions for lit signs ask for a photo of your disconnect.
Inside your sign: power supplies and low-voltage wiring
LED letters run from Class 2 power supplies that are listed for sign use or are part of a listed sign, and they sit inside your sign's body or a listed enclosure.
The wiring between letters is low-voltage Class 2 wiring, and wires that pass through your wall to remote power supplies go through a listed bushing.
Some wholesale power supplies are rated for dry locations only, so where they sit matters. Wire length from a supply to its modules is limited by wire size; one maker lists 20 to 40 feet for 100 to 300 watt supplies.
A raceway keeps power supplies reachable by removing its top, while a wireway can mean taking your whole sign down to reach them. See raceway or direct mount.
The UL label tells your inspector your sign was built to a safety standard.
Electric signs, section signs and retrofit kits must be listed and installed as their listing says. UL 48 is the standard for electric signs, and UL's program lets makers certify custom signs, including channel letters and box signs, for dry, damp or wet locations.
Individual letters ship as section signs, each with its own label, and at least one wholesaler's listing leaves out its raceway. Markings show who made your sign and its input voltage and current.
St. Petersburg's sign permit checklist asks for listing and labeling, including UL listing, on lit signs, and Pinellas County's inspectors ask for a photo of the listing mark. One national landlord bars any label on the exposed face except those an ordinance requires.
See UL label and the other electrical words in our glossary.
A photocell, a time clock or both turn your sign on and off.
A photocell turns your sign on at dusk and off at dawn, and a time clock switches it on a schedule. One national landlord's criteria ask for a photocell plus an outside on/off switch and do not allow a time clock alone.
Pinellas County's inspection instructions ask for a photo of your sign's method of control.
Lit signs have water and height rules too.
A lit sign in a wet location that is not listed as watertight needs drain holes at its low points. A sign over an area open to vehicles needs at least 14 feet of clearance unless it is protected.
See signs in Florida weather for what water and surges do to power supplies.
Your permit covers the electrical side, and an inspector checks it.
St. Petersburg's sign permit checklist asks for an electrical scope of work and cost breakdown, and all wall signs on one building can go on one application.
Pinellas County has separate permit types for wall signs with and without electrical work. Tampa runs an electrical final inspection along with its building final.
Florida is moving to a new edition of its building code, which brings a newer edition of the National Electrical Code with it. Ask your building department which edition applies when your application is filed.
What the county inspector asks to see
Pinellas County's inspection instructions for lit signs on county-issued permits, dated March 2026, ask for photos of these items.
| Item | What your photo shows |
|---|---|
| Posted permit | Your permit card on site. |
| Attachments and fasteners | How your sign is fastened, with fastener sizes. |
| Listing mark | The UL or other listing label on your sign. |
| Disconnect | The switch that cuts power to your sign. |
| Breaker and panel schedule | The breaker feeding your sign, marked on your panel schedule. |
| Method of control | Your photocell, time clock or switch. |
| Weep holes | The drain holes at your sign's low points. |
Cities with their own building departments, such as St. Petersburg, run their own inspections. See sign permits in Pinellas County.
Relighting an old sign has its own listing rules.
LED retrofit kits are listed for relighting signs built to UL 48. A certified kit installed to its instructions leaves your sign's original listing intact, and your relit sign gets a retrofit label naming who changed it and with what.
A homemade kit turns your sign into field-modified equipment that needs the inspector's review, and many cities require a permit for a retrofit. One LED maker's retrofit guide calls for licensed electricians to connect its power supplies and remove neon transformers, and who may install a kit varies by city.
You can check any contractor's license yourself.
Florida's electrical licenses include a sign specialty license. A registered, locally licensed electrical contractor may only contract in the area where it is registered.
Look up any contractor's license on the Florida Department of Business and Professional Regulation's license site.
Who does what on a lit sign
This is the usual split under Florida licensing and published lease criteria. Your lease and your contract settle it for your sign.
| Task | Who usually does it |
|---|---|
| The 20-amp circuit and outlet at your entrance | You or your tenant, as your lease says. |
| Main service terminations | Your landlord, in some lease criteria. |
| The branch circuit up to your sign's disconnect | An electrical contractor. |
| Wiring and power supplies inside your sign | A sign specialty electrical contractor. |
| The listing and its labels | The listed sign maker. |
| The electrical permit and inspection | A licensed contractor applies, and your city or county inspects. |
Questions to ask whoever builds your sign
- Is my sign listed, and whose label will it carry?
- Who makes the final connection?
- Is there a sign circuit at my entrance, or does one need to be run?
- Who pulls the electrical permit?
- Where will the power supplies sit, and how are they reached for service?
Not lit at all?
Non-lit letters need no sign circuit, but exterior letters still need a sign permit, and Pinellas County inspects non-electrical wall signs too. See choosing a sign type and dimensional letters.
Tell us what's at your entrance now, and send Tom a photo of your wall.
Let us know whether a sign outlet is already there and where your electrical panel is.